SAS has successfully completed a wide variety of significant projects across Australia.
Here is a sample of our work, please scroll down to find out more about each Project.
Here is a sample of our work, please scroll down to find out more about each Project.
Newmont Gold Pty Ltd
Location: Boddington Goldmine, Western Australia
|
SAS has completed a wide range of notable projects at Newmont Gold Mine over recent years, with our permanent onsite team as well as shut works where we had teams of up to 20 personnel working with Duratec and G&S Engineering.
|
Duratec Limited
Location: Boddington, Western Australia
Duration: March 2019 - October 2020 Total Employees onsite: 5 Contract Value: $135,000 This project involved shop fabrication of structural steel Mill Bridges, handrails and grid mesh that required specific S4 coatings. SAS were also tasked with the opportunity to remove the old Mill Bridges on site at Boddington then install the new Mill Bridges working with rope access company Brieght.
|
GMF ContractorsLocation: Neerup, Western Australia
|
G&S Engineering
Location: Gove, Boddington Gold, Yandi, FMG Shutdown, Soloman Shutdown
Duration: June 2019 - December 2019 Total Employees onsite: 3 Contract Value: $126,000 Most of these sites SAS were involved as a Superintendent with two apprentice roles including shutdown works and remediation works.
|
SIMPEC
Location: Cataby Iluka
|
Kaefer Maicon
Location: Geralton / Roxby Downs
Duration: September 2018 - October 2018 Total Employees onsite: 2 Contract Value: $80,000 This role was on a contract basis at two locations, Karara and BHP Olympic Dam. SAS Managing Director Murray Middleton and two of his apprentices performed shutdown work and structural remediation.
|
Interquip Resource Construction
Location: Tanamai Gold Mine
|
Eastern Goldfields
Location: Daveyhurst Mine
Duration: August 2016 Total Employees onsite: 7 Contract Value: $100,000 Shop fabrication and onsite construction of the Gold Mine core shed. This involved steel erection, insulation, installation, cladding of the structure, installation of roller doors and P/A doors.
Refurbishment of the maintenance shed that required removal of old cladding and purlins installation of new purlins insulation and cladding. |
McGrath Homes
Location: Various sites
|
Hare & Forbes
Location: Kewdale, Western Australia
Duration: December 2015 - April 2016 Total Employees onsite: 5 Contract Value: $124,000 SAS installed the fire water system as well as commissioning and shop fabricated structural steel and installed for the new show rooms Kewdale.
|
Thunderbox Project
Location: Between Leinster and Lenora, Western Australia
|
SAS Crew Onsite:
|
Matilda GoldLocation: Marble Bar, Western Australia
Duration: September 2015 - Current Total Employees onsite: 14 Contract Value: SAS were engaged by Interquip to help complete a shutdown on the Mt Webber Iron Ore Project for BGC.
|
SAS Crew Onsite:
|
Sino IronLocation: Cape Preston, Western Australia
Duration: September 2014 - September 2015 Total Employees onsite: 15 Contract Value: $2.5 million SAS were engaged by Kerman to help complete their contractual requirements at Sino Iron Project.
|
SAS Crew Onsite:
|
SAS Crew Onsite:
|
Karara Iron OreLocation: 200kms East of Geralton, Western Australia
Duration: August 2012 - April 2013 Total Employees onsite: 8 Contract Value: $1.5 million SAS was engaged by AGC to help complete their contractual requirements at the Karara Iron Ore Project.
|
SAS Crew Onsite:
|
Brockman 4 ProjectLocation: Pilbara Region, Western Australia
Duration: July 2012 - December 2012 Total Employees onsite: 25 Contract Value: $1.2 million SAS were engaged by Leighton Contractors to help complete their contractual requirements at the Brockman 4 Project.
|
SAS Crew Onsite:
|
Pluto LNG ProjectLocation: Karatha, Western Australia
Duration: February 2010 - December 2011 Total Employees onsite: 65 Contract Value: $8 million SAS were engaged by UGL Resources to help meet their contractual requirements at the Pluto LNG Project.
|
SAS Crew Onsite:
|
Gas Turbine Power StationLocation: Stove Hill, Karratha, Western Australia
Duration: October 2009 - 13 weeks Total Employees onsite: 13 Contract Value: $1.5 million SAS were engaged by United Group Resources to help meet their contractual requirements at Stove Hill.
|
SAS Crew Onsite:
|
Boddington Gold Mine Expansion ProjectLocation: Boddington, Western Australia
Duration: November 2008 - 8 months Total Employees onsite: 40 Contract Value: $3.5 million SAS were asked to provide 40 men for the Boddington Mine when the GFC hit. UGL kept all SAS men onsite during this time.
|
SAS Crew Onsite:
|
Industrial Shed Erection - Waddell Power StationLocation: Darwin, Northern Territory, Australia
Duration: July 2008 - 4 weeks Total Employees onsite: 13 Contract Value: $1.5 million SAS were engaged by United Group Resources to help complete their contractual requirements at the Waddell Power Station. SAS constructed a cyclone proof shed to turn key stage.
|
SAS Crew Onsite:
|
Major Maintenance Shutdown - Burrup Fertiliser Plant, DampierLocation: Dampier, Western Australia
Duration: May 2008 - 10 weeks Total Employees onsite: 33 Contract Value: $400,000 SAS were engaged by PSS Asia to help complete their contractual requirements at the Berrup Fertiliser Plant.
|
SAS Crew Onsite:
|
Industrial Shed Erection - Nifty Copper OperationLocation: Nifty Copper Mine, Australia
Duration: October 2007 - until completion Total Employees onsite: 6 Contract Value: $130,000 SAS were engaged by Weld Guard to construct an industrial size structure as required onsite at Nifty Copper. SAS provided construction of a 50m x 20m x 10m industrial structure. Complete to turnkey and consisting of a gantry crane and four sliding doors.
|
SAS Crew Onsite:
|
SAS Crew Onsite:
|
Theiss - PEU ConstructionLocation: Alcoa, Pinjarra, Western Australia
Duration: 2005 - 3 months Total Employees onsite: 8 Contract Value: $750,000 SAS were engaged by Theiss to help assist with their contractual requirements at the Pinjarra Efficiency Upgrade.
|
SAS Crew Onsite:
|
Downer ENG - Construction of the Alinta Cogneration Power StationLocation: Alcoa, Pinjarra, Western Australia
Duration: 2005 - 5 months Total Employees onsite: 8 Contract Value: $1.2 million SAS were engaged by Downer Engineering assist with their contractual requirements onsite at the HRSG Power Station.
|
SAS Crew Onsite:
|